Installing Generators

To power our HQ datacenter, we have purchased two diesel generators. They have arrived at PSP about a week ago and people from VECA and PSR are working very hard to install those generators.

While VECA is connecting the generators to the power panels, PSR is working hard to install exhaust pipes.